MODULE 09
Overheads, Risk & Margin
Site & Head-Office overheads and contingency are applied as a percentage on direct cost (Materials + Logistics + Manpower + Equipment + Indirects + Subcontracts). Profit is shown as the residual (Contract − Total Cost). Adjust any % to see the impact on margin instantly.
% LOADINGS
| Site Overheads | 236,007 SAR | |
| Head-Office Overheads | 314,676 SAR | |
| Contingency / Risk | 157,338 SAR | |
| Profit% (informational, residual) | Override only — actual margin shown on the right. |
FORECAST P&L
| Direct Cost | 7,866,893 SAR |
| + Site OH (3%) | 236,007 SAR |
| + HO OH (4%) | 314,676 SAR |
| + Contingency (2%) | 157,338 SAR |
| = Total Cost | 8,574,914 SAR |
| Contract Value (ex-VAT) | 8,826,700 SAR |
| FORECAST MARGIN | 251,786 SAR (+2.9%) |