Materials Cost — All materials, ex-VAT

Pre-loaded: SANCO supply prices for blocks · Class S mortar · Bed-joint reinforcement Z275 · Hilti HIT anchors · SS-304 ties · PU sealants · pre-cast lintels · in-situ RC stiffeners · sample panels. All quantities, wastages and unit prices are editable. Cost = Qty × (1+Wastage) × Unit Price.
BLOCKS
DescriptionSupplierUnitQtyWaste %Unit PriceLine Cost (SAR)
301,357
164,410
1,782,899
961,092
293,180
47,968
271,739
Sub-total — Blocks3,822,645
MORTAR
DescriptionSupplierUnitQtyWaste %Unit PriceLine Cost (SAR)
438,688
Sub-total — Mortar438,688
REINFORCEMENT
DescriptionSupplierUnitQtyWaste %Unit PriceLine Cost (SAR)
341,202
Sub-total — Reinforcement341,202
ANCHORS & TIES
DescriptionSupplierUnitQtyWaste %Unit PriceLine Cost (SAR)
223,135
19,127
Sub-total — Anchors & Ties242,262
SEALANTS
DescriptionSupplierUnitQtyWaste %Unit PriceLine Cost (SAR)
17,879
Sub-total — Sealants17,879
LINTELS & STIFFENERS
DescriptionSupplierUnitQtyWaste %Unit PriceLine Cost (SAR)
68,495
317,240
Sub-total — Lintels & Stiffeners385,735
SAMPLE PANELS
DescriptionSupplierUnitQtyWaste %Unit PriceLine Cost (SAR)
17,500
Sub-total — Sample Panels17,500
GRAND TOTAL — MATERIALS5,265,911 SAR